Provisions the documents cite: whole standards — the test methods behind the classification a penetration seal, linear gap seal, fire damper or fire-resisting duct system carries; cited so that a site record names the tested configuration the installation must match
What it requires
The fire-resistance classification printed on a seal or damper data sheet is only valid for the configuration tested. The quality sheets ask the installer to record the tested detail reference for every seal, barrier and damper, and to install nothing outside it.
How this entry is kept current
- Citation status: carried from drafting; a source check is in the monthly scan queue.
- Watched by: check for amendment, withdrawal or a new edition at each monthly horizon scan.
- Automated scan: no public page to watch; checked by hand in the monthly review.
Every source is re-checked monthly and the result is published in the scan log. A change that alters what a document should say raises a revision, and past buyers of that document are told.
The 25 documents that cite it
Every KubitDocs document prints its statutory basis on the form itself, so the person signing can verify the citation rather than take our word for it.
Ceilings and access floors quality checklists
- Ceiling Grid — Level and Hangers — Quality Inspection Checklist
- Ceiling Tiles and Access Panels — Quality Inspection Checklist
- Ceiling Void Close-Out — Quality Inspection Checklist
- Raised Access Floor — Quality Inspection Checklist
Inspection and test plans
Mastic and sealant quality checklists
- Fire-Rated Joints and Linear Gaps — Quality Inspection Checklist
- Movement and Perimeter Joints — Quality Inspection Checklist
- Wet-Area and Sanitary Sealing — Quality Inspection Checklist
Partitions quality checklists
- Demountable and Glazed Partitions — Quality Inspection Checklist
- Fire and Acoustic Wall Completion — Quality Inspection Checklist
Passive fire protection quality checklists
- Cavity Barriers and Fire-Stopping in Voids — Quality Inspection Checklist
- Compartment Line Walk Before Ceilings Close — Late Penetrations and Damage — Quality Inspection Checklist
- Fire Door Surveys and Remediation — Quality Inspection Checklist
- Fire-Rated Ductwork and Fire Dampers — Quality Inspection Checklist
- Intumescent and Board Fire Protection to Structural Steel — Quality Inspection Checklist
- Penetration Seals — Every Penetration Labelled and Photographed — Quality Inspection Checklist
- Service Risers and Shafts — Fire-Rated Floors, Walls and Riser Doors — Quality Inspection Checklist
Plastering and drylining quality checklists
- Boarding — Layers and Fixings — Quality Inspection Checklist
- Dry Lining on Dabs — Quality Inspection Checklist
- Fire-Stopping at Heads and Services — Quality Inspection Checklist
- Insulation and Acoustic Infill — Quality Inspection Checklist
- Metal Framing and Deflection Heads — Quality Inspection Checklist
- Services in the Wall and Pattresses — Quality Inspection Checklist
- Skim and Float — Flatness — Quality Inspection Checklist
- Taping, Jointing and Finish Level — Quality Inspection Checklist