Provisions the documents cite: the test method fire-rated partitions and linings are classified against; cited so the tested detail can be named
What it requires
Fire-rated partitions are only as good as the tested configuration. The checklists require the test or assessment report to be on site and the installed build-up to match it — this is the standard that report cites.
How this entry is kept current
- Citation status: carried from drafting; a source check is in the monthly scan queue.
- Watched by: BSI product record check each scan.
- Automated scan: no public page to watch; checked by hand in the monthly review.
Every source is re-checked monthly and the result is published in the scan log. A change that alters what a document should say raises a revision, and past buyers of that document are told.
The 11 documents that cite it
Every KubitDocs document prints its statutory basis on the form itself, so the person signing can verify the citation rather than take our word for it.
Inspection and test plans
Partitions quality checklists
- Demountable and Glazed Partitions — Quality Inspection Checklist
- Fire and Acoustic Wall Completion — Quality Inspection Checklist
Plastering and drylining quality checklists
- Boarding — Layers and Fixings — Quality Inspection Checklist
- Dry Lining on Dabs — Quality Inspection Checklist
- Fire-Stopping at Heads and Services — Quality Inspection Checklist
- Insulation and Acoustic Infill — Quality Inspection Checklist
- Metal Framing and Deflection Heads — Quality Inspection Checklist
- Services in the Wall and Pattresses — Quality Inspection Checklist
- Skim and Float — Flatness — Quality Inspection Checklist
- Taping, Jointing and Finish Level — Quality Inspection Checklist